The Hub Timescale

The Hub Timescale

Spring 2009: Planning Permission awarded

June 2010: Main funding agreements in place

Spring 2010: Highway works including new cycle facility off Station Street

July 2010: Award multi storey car park contract

December 2010: Multi storey car park building begins

January 2011: Award contract for main station works

February 2012: Car park open

May 2014: Main station works complete

Autumn 2014: NET Phase Two opens